View from La Finca looking out to the old castle - Castillo Arabe de Lojuela


Introduction to the Project
Outline layout
Log of progress on the Land
Our project plans
Planting and landscaping
Before, during and after images
The team
Contact us
Casa Amelia Homepage

Google
Casa Amelia pages
the web





Foundations of chicken run



BUILDINGS


A range of outbuildings are required so that we can begin to farm the land. At the very least, we need to construct a chicken run, storage for tools and equipment, a shaded area and toilet facilities.

The water deposit is also a critical construction project made more difficult by the need to locate it on the highest terraces.

Cement mixer and breeze blocks

Most of these outbuildings will be constructed on the lowest right-hand terrace (R0) which is the best area to minimise the impact on the views both of the land from the valley and on the land itself. We will also be planting trees and shrubs along the edge of this terrace to obsure these esential buildings.

Foundations for chicken run

Planning permission for the main house is progressing slowly, but this is not a problem at the moment as there is so much else that needs to be done first.



Chicken Run

The Chicken Run is on the far right end of the bottom right-hand terrace (R0). Two fenced compounds have been built either side of a 2x3m chicken house that will be home to between 10-20 chickens. It is not possible to have free-range chickens because of the risk from predators, however, the compound is quite large. It has been split into two sections so that the earth can be rested from time to time. Roughly every three months the chickens will be moved from one side to the other.

Chicken Run

TOP OF PAGE



Storage

Two temporary steel storage units have been erected onto a concrete base at the end of the bottom right-hand terrace (R0) next to the Chicken Run. These temporary stores allow us to keep equipment protected from the elements.

Steel stores

TOP OF PAGE



Pergola shade

A pergola has been constructed on one of the central terraces (C2). This will provide some shelter from sun in the summer and rain in the winter.

Pergola

TOP OF PAGE



Water Deposit

The water deposit is the most critical construction work on the land. Planning permission was required, and granted on 21 September. This deposit is a steel circular structure 3m high and just over 8m in diameter that will hold 150,000 litres of water.

The deposit had to be built on the highest terrace so that the irrigation can flow down to the rest of the terraces. Unfortunately that also means that it is in one of the most difficult areas to access. The original plan estimated that construction would take about 20 man days over the course of 2 weeks. So far the work has taken about 55 man days and a further 10-15 man days are required to finish the work.

A JCB digger had to be used to dig out an area big enough to construct the base (the original terraces were only about 4m wide). The digger spent about a day widening access routes so that it could get up to the terrace and a further 3 days digging out the base and moving the earth to lengthen terraces C9, R10 and R11.

JCB digging out the foundations

A complex iron mesh framework for the base had to be made, as shown in the diagram below. All the iron materials were carried up hill by hand and the framework constructed on site. This took Patrik and Tomas almost two weeks to complete.

Water Deposit Technical Diagram

Iron mesh framework

We had to source a specialist mini-cement mixer that we hired, along with a small dumper. The dumper was used to move sand, cement and water to a staging-post half-way up the hill (a large flat area between C7 and R5).

The 2 Peters and Tomas filling the base with cement

The first 1m high ring of the steel water deposit had to be aligned with the deepest foundations and set in about 10cm of concrete.

Patrik, Tomas and the 2 Peters working on the first ring of the steel water deposit

TOP OF PAGE



Select these links to find out more about the project.

Introduction   Outline layout   Log of progress on the Land
Our project plans   Planting and landscaping
Before, during and after images   The team


Location for pergola






























Foundations for storage sheds


Casa Amelia at La Finca de Castillo de Los Moros is in the Lecrín Valley south of Granada, Spain.
Email enquiries: info@casaamelia.com