|









|
|
LAND LOG:
December 2005
Highlights: Irrigation pipes delivered
And low-lights: Road works on the campo track disrupts work and deliveries
Other logs:
- Recent progress
- November 2005
- October 2005
- September 2005
- Earlier in 2005
Slow progress was made on the land in December 2005 - partly because of Christmas holidays but also as a result
of road works on the campo track that made it impossible for any deliveries for most of the month.
Scarlett bought bicycles for Patrik and Tomas, at their request, so they could continue to get to the land and make some progress using up the materials that were already at the land.
One day the boys cycled to the land carrying ladders between them on their 2 bikes, so they could finish work on the water deposit. Unfortunately we did not manage to capture this on camera but you could just imagine the scene as being something from an old 1930s Buster Keaton movie!
The boys did mange to get themselves and the ladders to the land in one piece, so they were able to finish the construction of all 3 layers of the steel water deposit (shown above).
There were also enough materials on the land to complete the chicken house construction. However, the roof of the chicken house was blown off in high winds only a few hours after they had finished it.
The pergola roof tiles are another victim of the winds - each week a little bit more blows away. A complete replacement is required, but this will probably have to wait until higher priority items are finished, such as the water deposit and irrigation system.
Eventually, on 19 December, the campo road was open again - although with a few pot hole - but it was good enough for us to be able to take delivery of all the irrigation system (pipes, taps, joints, etc).
The delivery lorry was able to get into Murchas and the Boys were able to use the car and trailer to move the materials from their to the land bit by bit.
Land logs from other months:
2007 Summary
Summer 2006
Spring 2006
February 2006
January 2006
November 2005
October 2005
September 2005
Earlier in 2005
Select these links to find out more about the project.
Introduction
Outline layout
Our project plans
Planting and landscaping
Building activities
Before, during and after images
The team
|
|
|